The Factory Acceptance Test (FAT) was successfully conducted for four prefabricated container-type substations that will be installed within the energy complex of the "Kapino Polje" solar power plant, whose investor is Elektroprivreda Crne Gore (EPCG).
The tests, in the presence of XEnergy representatives, were conducted at the CHINT Power Systems factory in the Chinese city of Huainan, Anhui Province, one of the leading production sites within the CHINT Group, a global manufacturer of energy equipment.
The substations have a power of 7 MVA, voltage ratio 10/0.8 kV, and will be the first units of this type installed in Montenegro. The substations will serve as the main node between the solar panels and the power grid, raising the voltage from 0.8 kV to 10 kV and ensuring a stable and safe delivery of energy.
The Kapino Polje solar power plant is being implemented in four phases (L1, L2, B1 and B2), and the last published technical data shows that the Kapino Polje B1 power plant will have an installed power of 11.43 MWp and an expected annual production of close to 15.8 GWh, which is enough to supply several thousand households.
Prefabricated substations play an important role in the operation of solar power plants, because they ensure the raising of the voltage from the output level of the solar inverters to the level required for connection to the power grid. In addition, substations enable the protection, supervision and quality control of the supplied energy, which ensures stable and safe operation of the system as a whole.