On Thursday, January 29, XEnergy will start preliminary works within the project "Regional Program for Energy Efficiency in Transmission - Component II: Montenegrin Coast, Luštica Region Development", LOT 2.
LOT 2 includes the installation of approximately 10,415 km of underground double 110 kV cables, on the route from the new 110/35 kV GIS substation Radovići to pole no. 170, as well as connection to the existing 110 kV overhead transmission line Lastva-Tivat, using a line-in-line-out (LILO) configuration.
The project is being implemented for the investor Crnogorski elektroprenosni sistem ad (CGES), with the financial support of KfW Entwicklungsbank, while the supervision of the implementation is carried out by GOPA Tech GmbH.
Preliminary works include site preparation, additional geodetic and topographic surveys, organization of temporary installations, earth and concrete works, as well as all activities defined by the approved project and E&S documentation.
A multidisciplinary team of experienced engineers was engaged in the project, with a focus on compliance with all technical, regulatory and contractual requirements, as well as health, safety and environmental protection standards. Works are performed in accordance with current legislation, international standards and approved plans. This project represents an important step in strengthening the reliability of the transmission power network on the Montenegrin coast and improving the overall energy stability of the system.